Wednesday, April 1


T’puram: Construction of Sreekaryam flyover, a key preparatory component of the proposed Metro rail system in the state capital, is progressing steadily, with authorities aiming to complete critical preliminary works ahead of the monsoon.The project, being executed by Kochi Metro Rail Ltd (KMRL), has witnessed significant headway in recent weeks. The tarring of one side of the service road was completed last week, and work is currently focused on finishing the remaining stretches of service roads. The contractor, Cherian Varkey Constructions Ltd, is targeting completion of these works before the onset of the monsoon. However, officials said the commencement of piling work for the main flyover structure has been delayed due to ongoing pipeline-laying activities under AMRUT (Atal Mission for Rejuvenation and Urban Transformation) scheme. Once these utility works are completed, piling is expected to begin by June. Sreekaryam flyover project forms part of a larger urban mobility plan linked to the proposed Thiruvananthapuram Metro. The Metro system, to be implemented by KMRL, is envisioned as a modern rapid transit network spanning multiple corridors across the city to ease traffic congestion and improve connectivity. According to officials, foundational infrastructure works at Sreekaryam are nearing completion. “Drain construction and utility ducts have already been finished, while utility shifting activities are progressing. Earlier reports indicate that nearly 90% of stormwater drain work was completed as part of the initial phase,” a source said. The flyover itself is designed to integrate seamlessly with the future Metro corridor. Engineering plans include provisions for Metro pillars to be installed along the median, ensuring that the elevated road infrastructure can support future transit expansion without major modifications. The flyover, spanning 535m with 17 spans, will serve as a shared structure for both the flyover and Metro rail corridor. The foundation stone for the flyover was laid in Jan 2025, marking beginning of on-ground work after years of planning. The project is part of a broader infrastructure push that includes similar flyovers at Pattom and Ulloor, aimed at decongesting some of the busiest stretches in the city. Despite procedural delays affecting the Metro’s detailed project report (DPR), preparatory works such as the Sreekaryam flyover are being pushed forward to maintain momentum. Delhi Metro Rail Corporation is currently revising the DPR, incorporating alignment changes and updated technical assessments.KMRL is executing the Rs 177 crore project, funded through KIIFB. Of this, Rs 71.38 crore was earmarked for core structure. Land acquisition of 1.34 hectares involving 168 properties across Cheruvakkal, Ulloor and Pangappara was completed in late 2024, with Rs 98 crore disbursed in compensation. A total of 168 buildings were demolished to make way for the project.



Source link

Share.
Leave A Reply

Exit mobile version